You can move the circuits you use every day onto your own solar and batteries, and keep your Hawaiian Electric connection for cloudy weeks and big appliances. Done the right way, with a switch that never lets the two systems touch, it needs a county permit but no utility interconnection application.
At about 48¢ for every extra kWh from the grid, each kWh you make and use yourself is worth a lot, and the hybrid approach lets you capture that without a utility interconnection application, export limits or program rules that can change under you. Moving your everyday loads to your own solar and batteries cuts your bill, keeps the fridge, lights, internet and water pump running through outages, and leaves the grid on call for cloudy weeks and big appliances. The catches: you can’t sell or bank surplus power, so midday sun beyond what your battery holds goes unused; you need more battery than a grid-tied system would; the separate panel, transfer switch and rewiring add cost; you still pay the monthly customer charge; and your savings shrink if oil prices, and with them electric rates, fall. You also become the operator of a small power plant. A grid-tied battery system under one of Hawaiian Electric’s programs can do much of the same and earn credit for exports, so it is worth getting quotes for both.
Your solar, batteries and inverter feed a separate solar loads panel. A transfer switch lets that panel take power from either your inverter or the grid, but it physically breaks one connection before it makes the other, so your solar can never push power onto utility lines. Pick a design and a situation below, and click any part to learn what it does.
Hawaiian Electric’s interconnection rules cover generators that operate in parallel with its grid. A system that is only ever connected to your loads, or to the grid, but never both at once, isn’t interconnected. It is still a solar installation, though, so it needs county permits, code-compliant equipment and a licensed electrician.
The PUC describes Rule 14H as governing distributed generators “operating in parallel” with the utility’s system. A break-before-make transfer switch keeps your inverter and the grid apart, the same way a backup generator is hooked up.
Hawaiian Electric’s own safety guidance: an auxiliary power system may only be connected to house wiring through an approved transfer switch, installed by a qualified electrician under the National Electrical Code and state and local codes.
Hawaiʻi County requires a permit for any complete new solar installation. Residential systems over 10 kW (cumulative) also need plans stamped by a licensed electrical engineer. The county’s energy code even refers to “permitted, off-grid, self supplying photovoltaic with battery back up.”
Hawaiʻi adopted the 2020 National Electrical Code. The articles that matter: 690 (solar), 706 (batteries), 710 (stand-alone systems), 702 (transfer equipment) and 250.30 (grounding a separately derived system).
State adoption of the 2020 NEC · Explainer: Articles 702–710
Tick the loads you would put on the solar loads panel and adjust the hours. The planner sizes the solar, battery, inverter and transfer switch, and estimates what you would stop buying from the grid. These are rough planning numbers to take to a licensed installer, not a design.
Rough rules of thumb. For your exact address, run NREL PVWatts.
The grid covers the rest on cloudy stretches. Going from 90% to 100% takes a lot more panels and battery.
With the grid as backup, one day is usually enough. More helps in long outages.
Default: 48¢, the cost of each added kWh on a Hawaii Electric Light residential bill in November 2026 ($243.16 at 500 kWh, $291.18 at 600 kWh, per the fuel-charge filing). It changes monthly with oil prices.
Share of a typical 500 kWh/month bill this covers: 0%
Assumes lithium iron phosphate (LFP) batteries at 90% usable depth and 95% round-trip efficiency, 420-watt panels and 77% system derate. Peak load assumes your biggest load plus half of the rest at once. You still pay the grid’s monthly customer charge, and savings fall if oil prices do.
Use the planner. Most homes move the fridge, lights, fans, internet, pump and outlets, and leave the range, dryer and EV charger on the grid.
A licensed electrical contractor (and an engineer over 10 kW) draws the system: transfer switch type, whether the neutral must be switched, wire and breaker sizes, labels.
Apply through the county’s EPIC system with the plans and equipment specs: UL 1741 inverter, UL 9540 battery system, listed transfer switch.
The electrician moves the chosen circuits to the new panel and installs the switch, disconnects and placards. The county inspects before you energize.
Lock export and grid-assist settings off, keep your permit and inspection records, and tell your insurer about the system.