Think B.I.G.← Back to the Toolbox
Toolbox · Solar & storage

The hybrid option: your own solar for most of the house, the grid as backup

You can move the circuits you use every day onto your own solar and batteries, and keep your Hawaiian Electric connection for cloudy weeks and big appliances. Done the right way, with a switch that never lets the two systems touch, it needs a county permit but no utility interconnection application.

0¢what each extra kWh from the grid costs a Big Island home (Nov. 2026)
0utility applications for a system that never runs in parallel with the grid
1county permit you still need, with a licensed electrician doing the work
SOLARLOADS transfer switch: solar OR grid, never both
Why go hybrid?

The case for it, and the catches

At about 48¢ for every extra kWh from the grid, each kWh you make and use yourself is worth a lot, and the hybrid approach lets you capture that without a utility interconnection application, export limits or program rules that can change under you. Moving your everyday loads to your own solar and batteries cuts your bill, keeps the fridge, lights, internet and water pump running through outages, and leaves the grid on call for cloudy weeks and big appliances. The catches: you can’t sell or bank surplus power, so midday sun beyond what your battery holds goes unused; you need more battery than a grid-tied system would; the separate panel, transfer switch and rewiring add cost; you still pay the monthly customer charge; and your savings shrink if oil prices, and with them electric rates, fall. You also become the operator of a small power plant. A grid-tied battery system under one of Hawaiian Electric’s programs can do much of the same and earn credit for exports, so it is worth getting quotes for both.

How it works

Two power systems, one switch between them

Your solar, batteries and inverter feed a separate solar loads panel. A transfer switch lets that panel take power from either your inverter or the grid, but it physically breaks one connection before it makes the other, so your solar can never push power onto utility lines. Pick a design and a situation below, and click any part to learn what it does.

Design
Situation
Solar array PV disconnect + rapid shutdown Inverter-charger stand-alone mode export / “grid assist”: OFF Battery fuse + disconnect Battery (LFP) Transfer switch INVERTER GRID Solar loads panel • refrigerator, freezer • lights, fans • Wi-Fi, TV, laptops • water pump, washer • outlets you choose Main panel grid-only loads: range, dryer, water heater, EV breaker → switch utility meter Grid grid-input breaker No path back to the grid: line crews stay safe
solar powerbattery powergrid powerno current

Is it legitimate?

Yes, if the two systems never run together

Hawaiian Electric’s interconnection rules cover generators that operate in parallel with its grid. A system that is only ever connected to your loads, or to the grid, but never both at once, isn’t interconnected. It is still a solar installation, though, so it needs county permits, code-compliant equipment and a licensed electrician.

1

No utility application, if it never parallels

The PUC describes Rule 14H as governing distributed generators “operating in parallel” with the utility’s system. A break-before-make transfer switch keeps your inverter and the grid apart, the same way a backup generator is hooked up.

PUC: Rule 14H approval (2011)

2

An approved transfer switch, installed by a pro

Hawaiian Electric’s own safety guidance: an auxiliary power system may only be connected to house wiring through an approved transfer switch, installed by a qualified electrician under the National Electrical Code and state and local codes.

Hawaiian Electric: Generator safety

3

County permits still apply

Hawaiʻi County requires a permit for any complete new solar installation. Residential systems over 10 kW (cumulative) also need plans stamped by a licensed electrical engineer. The county’s energy code even refers to “permitted, off-grid, self supplying photovoltaic with battery back up.”

County DPW: permits · Bill 66 (2023) · County energy code

4

Built to the electrical code

Hawaiʻi adopted the 2020 National Electrical Code. The articles that matter: 690 (solar), 706 (batteries), 710 (stand-alone systems), 702 (transfer equipment) and 250.30 (grounding a separately derived system).

State adoption of the 2020 NEC · Explainer: Articles 702–710

The gray zone: inverters with a grid input (Design B). Many inverter-chargers can take grid power in, pass it through to your loads, and charge the battery. That alone is not parallel operation: an internal relay disconnects the grid before the inverter takes over. But features that blend inverter output with grid power (often called grid assist, power assist, peak shaving or grid support) or that sell power back do run in parallel with the grid, even if nothing is exported. If your equipment will ever do that, it is interconnected, and you need Hawaiian Electric’s approval under its Smart Renewable Energy Non-Export program (expedited, and batteries are allowed). Design A avoids the question entirely.
Never do this: plug an inverter or generator into a wall outlet, use a “suicide cord,” or wire a solar loads panel so it can be fed from both sources at once. Backfeed can kill line workers and neighbors. This page is general information, not legal or engineering advice; your electrician and engineer are responsible for the design.
Planner

What would you move to solar, and what would it take?

Tick the loads you would put on the solar loads panel and adjust the hours. The planner sizes the solar, battery, inverter and transfer switch, and estimates what you would stop buying from the grid. These are rough planning numbers to take to a licensed installer, not a design.

Rough rules of thumb. For your exact address, run NREL PVWatts.

The grid covers the rest on cloudy stretches. Going from 90% to 100% takes a lot more panels and battery.

With the grid as backup, one day is usually enough. More helps in long outages.

Default: 48¢, the cost of each added kWh on a Hawaii Electric Light residential bill in November 2026 ($243.16 at 500 kWh, $291.18 at 600 kWh, per the fuel-charge filing). It changes monthly with oil prices.

Your hybrid system, roughly

0
kWh a day moved to solar
$0
saved a month (≈ $0 a year)

Share of a typical 500 kWh/month bill this covers: 0%

    Assumes lithium iron phosphate (LFP) batteries at 90% usable depth and 95% round-trip efficiency, 420-watt panels and 77% system derate. Peak load assumes your biggest load plus half of the rest at once. You still pay the grid’s monthly customer charge, and savings fall if oil prices do.

    Getting it done

    Five steps, in order

    Choose your loads

    Use the planner. Most homes move the fridge, lights, fans, internet, pump and outlets, and leave the range, dryer and EV charger on the grid.

    Get a design

    A licensed electrical contractor (and an engineer over 10 kW) draws the system: transfer switch type, whether the neutral must be switched, wire and breaker sizes, labels.

    Pull the county permit

    Apply through the county’s EPIC system with the plans and equipment specs: UL 1741 inverter, UL 9540 battery system, listed transfer switch.

    Install and inspect

    The electrician moves the chosen circuits to the new panel and installs the switch, disconnects and placards. The county inspects before you energize.

    Run it and keep records

    Lock export and grid-assist settings off, keep your permit and inspection records, and tell your insurer about the system.

    Day to day

    Operating it safely

    Every month

    • Check battery charge and your inverter’s daily log; see how often the grid took over.
    • Exercise the transfer switch (or test the inverter’s transfer) so you know it works before you need it.
    • Rinse salt and dust off panels if output drops.

    When the grid goes down

    • Your solar loads keep running; the main panel goes dark. That is the switch doing its job.
    • Ration big loads at night: pump and washer in the sunny hours.
    • Do not try to back-feed the main panel “just this once.”

    Before anyone works on it

    • Put the transfer or bypass switch on GRID (or OFF), open the PV and battery disconnects, and use the rapid-shutdown switch.
    • Lock out and tag the disconnects.
    • Keep the one-line diagram and breaker list posted at the panel.

    Sources

    1. Hawaiʻi PUC press release: Rule 14H governs generators operating in parallel with the HECO Companies’ system (Nov. 29, 2011)
    2. Hawaiian Electric: Generator safety (approved transfer switch, qualified electrician, NEC)
    3. Hawaiian Electric: Smart Renewable Energy Non-Export program
    4. Hawaiʻi County Department of Public Works: Building permit information (solar PV)
    5. Hawaiʻi Tribune-Herald: Council passes Bill 66, engineer stamp only above 10 kW (Nov. 2023)
    6. Council adopts amended PV rules: stamp required when cumulative residential output exceeds 10 kW (May 2026)
    7. Hawaiʻi County supplement to the residential energy code (permitted off-grid PV with battery backup)
    8. State Building Code Council adoption of the 2020 National Electrical Code
    9. N.C. Office of State Fire Marshal: NEC Articles 702, 705, 706 and 710 explained
    10. Hawaii Electric Light: Energy Cost Recovery filing, Nov. 1, 2026 (typical bills at 500 and 600 kWh)
    11. NREL PVWatts calculator